Release Plan¶
Lezioni alla pari¶
April 19, 2020
Team Members¶
Ovidiu Andrioaia
David Cirdan
Luciano Mateias
Zhiyang Xia
Document Control¶
Change History
Revision | Change Date | Description of changes |
---|---|---|
V1.0 | 04/19/2020 | Initial release |
Document storage
This document is stored in the project's GIT repository at: https://github.com/KilliKrate/Software-Documentation-G6/blob/master/docs/Release%20Plan/index.md
Document Owner
Group 6 is responsible for developing and maintaining this document.
Table of Contents¶
Release #1: Release of the beta application¶
- Iteration #1: design all the application architecture and find partners
Features / Deliverables | Estimated Effort | Actual Effort |
---|---|---|
Architecture design | 10 hrs | 15 hrs |
Finding partners | 7 hrs | 10 hrs |
- Iteration #2: development of the database, front-end and back-end with beta release
Features / Deliverables | Estimated Effort | Actual Effort |
---|---|---|
Database development | 6 hrs | 11 hrs |
Front-end development | 30 hrs | 28 hrs |
Back-end development | 34 hrs | 30 hrs |
Beta release | 12 hrs | 14 hrs |
Release #2: Launch of the final application¶
- Iteration #3: final release, with the approval of partners, stakeholders and various software debugging
Features / Deliverables | Estimated Effort | Actual Effort |
---|---|---|
Software debugging | 20 hrs | 15 hrs |
Approval of partners, stakeholders | 5 hrs | 3 hrs |
Final release | 10 hrs | 13 hrs |
Effort Estimates (Hours)
Iteration 1 | Iteration 2 | Iteraton 3 | ||
---|---|---|---|---|
Iteration 1 | 17 hrs estimated | 25 hrs actual | 25 hrs actual | 25 hrs actual |
Iteration 2 | 82 hrs estimated | 82 hrs estimated | 83 hrs actual | 83 hrs actual |
Iteration 3 | 35 hrs estimated | 35 hrs estimated | 35 hrs estimated | 31 hrs actual |
Total: | 134 hrs | 142 hrs | 143 hrs | 139 hrs |